Project Updates

Court Street – Phase 1

Court Street Phase 1 roadway improvements began in May with sewer construction.The next phase of work will be electric and gas upgrades. Work is scheduled to be completed in December 2018.

Eversource will begin relocating utility poles and plans to relocate poles as necessary from Main Street to the Belmont town line.

Liberty Utilities will be upgrading gas lines within the Phase 1 area and from Rowe Court though the Main Street intersection and north on Union Avenue.

Phase 1 extends from Keasor Court to Fair Street and includes upgrades to drainage, sewer, water and sidewalks.

Pleasant Street – Oak Street to North Main

Pleasant Street roadway improvements are scheduled to begin in June and be completed by September 2018 to minimize impact to the Pleasant Street Elementary School.

Pleasant Street work includes upgrades to drainage, sewer and sidewalks.

Vehicles will be detoured around the construction zone.  Watch for detour signs and flaggers.

Bowman Street 

Bowman Street, from Academy Street to S. Main Street, is scheduled for water, sewer and drain upgrades and road reconstruction.

The first phase of work, water upgrades, has been completed. The next phase of sewer, drain and roadway improvements will begin in May an be completed by November 2018.

 

For other projects, see  CURRENT ROAD PROJECTS

For more information call

Project Manager: Krista Larsen  528-6379 ext. 306

On site inspector: Gordon Loud 528-6379 ext. 310